The Uttar Pradesh Code on Social Security Rules, 2026
Form XXXVII (B)
Official text
Open in the official PDF (p. 170)
Tables and forms lose their layout when extracted; the PDF is the authoritative version.
[See sub-rule (4) of Rule 88]
Record of Cess paid by the employer of building and other construction work
1 Name and address (permanent) of the establishment.
2 Name of the employer and address details
3 Name and address/ location of place where the building and other construction is proposed to be
carried on.
4 Name, designation and address of the authorised Person along with contact details
5 Correspondence address for the proposed building or other construction work may be sent
6 Nature of proposed construction work
7 Date of commencement of work(in case construction has
started)
8 Date of completion of work
9 Duration of work
10 Total completed area of construction work
11 Total estimated cost of the construction based on the rates of (UP-PWD or CPWD or RERA or
some other rates as the case may be) along with documents (original)
12 Total incurred cost of the construction work
13 Total amount of cess payable
14 Advance cess paid, along with details (at the time of approval of the Project or before the
commencement of the construction work) /deduction at source, if any
15 Details of cess paid (when duration of the proposed construction work is more than one
year)
Year
Amount
(in rupees)
st year
nd year
rd year
16 Total of the cess paid (Sl.No. 14 + 15)
17 Amount of outstanding cess (Sl. No. 13 – Sl. No.16)
18 Proof of payment of outstanding Cess, if any
19 Amount of overpaid cess, if applicable
20 Amount of cess assessed by the Assessing Officer
21 Amount of outstanding cess to be paid by the employer
22 Amount of penalty for non-payment of cess imposed / outstanding cess claimed by the Assessing
Officer.