The Gujarat Occupational Safety, Health and Working Conditions Rules, 2025
Rule 70. Certificate of Stability
Text read by machine from the official scan
(1) No manufacturing process shall be carried out in any premises of a factory constructed, reconstructed, altered, repaired or extended or increase in machinery or change in process in any existing factory until a Certificate of Stability in Form 32 in respect thereof, has been submitted to office of the Inspector-cum-Facilitator of factories.
(2) Certificate of Stability" in Form 32 shall be signed by Competent Person along with the tests, load calculation and analysis reports relating to stability:
Provided further that no manufacturing process shall be carried out in any premises of'a factory unless a fresh certificate of stability in Form 32 is obtained from a competent person once in each period of five years or after every extension, alteration, repairs or addition of machinery, plants etc. and sent to the Chief Inspector-cum-Facilitator of factories:
Provided also that. the foregoing provisions are without prejudice to the provisions of rules 48, 49.
Explanation: - "Work of engineering construction" means any building tank silo, scaffold, platform, chimney. bridge, supporting structural work, retaining wall or any similar structure.