The Gujarat Occupational Safety, Health and Working Conditions Rules, 2025
Rule 5. Fees
Text read by machine from the official scan
(a) The fees to be paid through c-payment for the grant of a certificate of registration under rule 4 shall be as given below namely: - If the numberiof workers proposed to be employed in the factory/establishment on any day Number of workers Fees Up to 49 Rs. 500 50 t0 99 Rs. 1000 100 to 299 Rs.5000 300 and above Rs. 10000
(b) Late fees: here an employer has not submitted his application for registration within 60 days as required under sub-section (1) of section 3. he shall submit the application for registration along with late fee as under: Period of Delay Percentage of Fees Up to 30 days 5% Up to 60 days 10% Up to 90 days 15% Above 90 days 1% cvcryday