Rule 48. Time-limit for review under sub-section (7) of section 78

Chapter X — Special Provisions Relating to Lay-off, Retrenchment and Closure in Certain EstablishmentsMade under The Industrial Relations Code, 2020No. LAB(W) 11/2021, 17 Dec 2021

Official text

The State Government may, either on its own motion or on the application made by the employer or any worker, review its order granting or refusing to grant permission under sub-section (4) of the section 78 within a period of thirty days from the date on which such order is made.

Source: The Industrial Relation (Arunachal Pradesh) Rules, 2021, No. LAB(W) 11/2021 — Arunachal Pradesh Gazette Extraordinary No. 286, Vol. XXVIII, 23 December 2021, p. 17 of the PDF. Open our copy at p. 17 · official download · all sources