Deadlines · Social Security Code

Building cess: payment

What to do

Pay the building and other construction workers’ cess, at the rate the Central Government notifies within the limits in the Code, of up to two per cent of the cost of construction s. 100(1), in advance on a self-assessment certified by a chartered engineer rule 41(2)(a).

Who it applies to

Every employer undertaking building or other construction work s. 100(2).

When

In advance at the time of approval or before the work starts rule 41(2)(a), and the balance within sixty days of completing each project, after adjusting the advance s. 103(1).

How

Related obligations

Provisions cited (5)

All compliance obligations · Official text reproduced from the Gazette of India, India Code and State Government sources. This is not legal advice; check the source PDF before relying on any provision.