Deadlines · OSH Code

Paying contract labour when the contractor does not

What to do

If the contractor fails to pay the contract labour within seven days of the end of the wage period, pay the wages in full, or the unpaid balance, and recover the amount from the contractor rule 98(8) s. 55(3).

Who it applies to

Establishments in which fifty or more contract labour are employed, or were employed on any day of the preceding twelve months, through contract, and manpower supply contractors who have employed fifty or more contract labour on any such day s. 45(1).

In the checklist: Contract labour (OSH Code Chapter XI, Part I).

When

Within fifteen days rule 98(8).

How

Related obligations

Provisions cited (3)

All compliance obligations · Official text reproduced from the Gazette of India, India Code and State Government sources. This is not legal advice; check the source PDF before relying on any provision.